How to Fix a Road

I love trying to appreciate the invisible work that goes into making our day-to-day lives possible. Yesterday night, I spotted some road construction happening on El Camino Real and decided to stop and take some photos. I also learned a lot, and I'll try to share that as well.

From chatting with a couple folks, I learned that the task for last night was to fix some areas with deteriorating pavement, in preparation for repaving entire stretches of the street this (Tuesday) evening. Having frequently ridden my bicycle over at least one of the sections that they worked on last night, it was definitely it pretty rough shape.
The process starts by doing some research and marking the roadway for cut locations. The markings include sections of the road that should not be cut, such as any area with a metal cover.
A cold milling machine is the device that actually removes the old pavement. It's generally operated by two people, and the ground operator controls the cut depth, as well as fine maneuvering. Here, the ground operator checks the depth of the cut with a ruler as the machine moves away from him.
As the milling machine moves along, it leaves behind some powdered debris from the old surface. The workers used a skid loader, a backhoe with a special attachment, and shovels and rakes to collect, redistribute, and grade the powder as a kind of intermediate layer. They then steamrolled it flat.
After the intermediate layer is steamrolled, trucks bring in fresh, hot asphalt to dump into the cut area. I could feel the heat from where I was standing, 15 or 20 feet away. The backhoe grades the new asphalt with the help of a couple workers with hand tools.

Here, a worker finishes a banana while waiting for the backhoe to finish grading the new asphalt. As an onlooker, it's easy to forget that on-the-job nutrition is likely an important aspect of avoiding injury while working long hours.
Finally, the graded asphalt is steamrolled multiple times. Even so, vehicle traffic will continue to compress the new pavement well after the actual construction finishes.

As mentioned, though, this is only preparation for the next step, planned to happen this evening. Crews will take from 1 to 3 inches off of the entire width of the road surface and repave it.

5 comments:

Victoria Sellers said...

Hello Omari, I like this posting with the great night photos and 'how to' information. I too appreciate all that these construction workers do to improve our roadways. I consider what they do an 'artform,' as they pave or widen roads, build bridges, overpasses and make other necessary modifications that are meant to make our travels easier on the streets and highways. After their work is completed, it's sometimes hard to figure out how things were before the change. Even if we must adjust to the new changes, I have found that the changes made are always for the better.

Alasdair Mackintosh said...

Great pictures. I like the one of the skid-loader and the men with the rakes following it. There's a really strong horizontal composition here.

Doppler Photo said...

Thanks, y'all, I really appreciate it.

internazi said...

Very Nice presentation. If you need more pictures please have a look here.

http://www.heavyequipmentforums.com/forumdisplay.php?70-Mills

Doppler Photo said...

Hey, Johnny, thanks and thanks for the link. I just spent a half-hour looking through the photos on that site :o)

I had shot some milling one other time, about 3 years ago:
http://blog.doppler-photo.net/2009/10/roadwork-pt-2.html